Stark Pavement Corporation is schedule to start working on 56th Avenue starting Oct. 12.
The contractor will pulverize the road surface Monday and will instal new curbs and gutters the following days.
Final grading is schedule to happen Friday.
The binder and top coarse asphalt will be laid the week of Oct. 19.